Stanhope Gate

January 2024

Piling is now drawing to an end at Stanhope Gate which will kick off the excavation of the new double basement below the lower ground floor. Pre-piling we had to break out and remove 90m3 of 1500mm thick concrete using the latest robotic technology.

Our top-down programme is allowing us to be completing the lead roof finishes above the newly built level 6 duplex and installing the steel stair structure through levels 1 to 5.